Parking lots around the Delta Center are in the middle of downtown Salt Lake City, where paving comes with more to consider than the asphalt itself.

Morgan Pavement removed and replaced asphalt in parking areas around the basketball arena, with striping also part of our scope. Along with the pavement work, we had electrical poles and lighting to work around, traffic affecting access to the site, and the arena’s event calendar to consider.

Downtown Traffic and the Arena’s Event Calendar

Getting into and out of the downtown work area was one of the challenges on this job. Asphalt deliveries and paving equipment both needed access to the parking lots.

With a dump truck supplying material to a paver, vehicle movement was connected to the paving operation, not just the traffic on the surrounding streets.

The venue’s event schedule presented a different challenge. We were able to work around the building’s scheduled events while carrying out the project.

As the Federal Highway Administration explains in its guidance for permanent event venues, sports and concert crowds can create concentrated periods of arrivals and departures. That helps explain why paving near an arena requires attention to its calendar as well as ordinary downtown traffic. Both were real considerations at this location.

Paving Around Poles and Lighting

We had to work around numerous electrical poles and lighting features in the parking areas. Those fixed features left less room for paving equipment in some places than in the open sections of the lot.

During asphalt placement, a dump truck with its bed raised was positioned at the paver. Our crew also used hand tools alongside the equipment, including near the edge of the newly paved surface. A CAT paver and roller were at the work site.

The job involved both large machines and close work along the pavement edge, all within a setting that had existing features to navigate.

Asphalt paving includes material delivery, spreading, and rolling. Caltrans’ construction guidance addresses these as distinct operations. That equipment had to operate within the space available around the site’s poles and lighting.

Removing Asphalt, Replacing It, and Adding Striping

Our work involved removing existing asphalt and installing new pavement. In one part of the active work area, the dark newly placed asphalt met a lighter adjoining surface. That transition was visible as the crew continued working near the edge of the new pavement.

Removal and replacement is not the same as placing an asphalt overlay over the existing surface. The Federal Highway Administration distinguishes overlays from other pavement rehabilitation and reconstruction approaches. We took out existing asphalt before installing new pavement, rather than simply adding another layer on top.

Parking lot striping was part of the project as well. Parking lot lines define spaces and help organize how vehicles use the paved area.

For a downtown parking lot near a busy arena, the markings are a separate part of making the surface usable for parking, beyond the asphalt replacement itself.

Planning Commercial Asphalt Replacement in Salt Lake City?

If you’re planning commercial parking lot paving, the surrounding site deserves attention along with the surface. Existing poles, vehicle access, and nearby schedules can all matter. 

Request an estimate from our team and tell us about the asphalt work your property needs.

 